Garden home planning rules in Ireland
The Class 3A exemption, condition by condition, and what each one means in a real Irish back garden.
Since 27 July 2026 you can put a detached house of 32 to 45 m² in the rear garden of your home without planning permission, provided the project meets every condition of the Class 3A exemption. Class 3A was inserted after Class 3 in Part 1 of Schedule 2 of the Planning and Development Regulations 2001 by S.I. 340 of 2026, signed on 16 July 2026. Miss one condition and the build is not exempt, which is why this page goes through them one at a time.
Class 3A at a glance
- Where: the rear garden of your main house.
- Size: not less than 32 m² and not more than 45 m². Under the Department's clarification, a shed already in the garden does not count towards the 45 m².
- Height: 4 m with a tiled or slated pitched roof, otherwise 3 m.
- Garden left over: at least 25 m² of private open space for the main house.
- Boundaries: at least 0.6 m from any wall or party boundary.
- Services: no separate utility connection.
- Paperwork: notify your council at least 14 days before work starts.
- Deadline: commenced and completed by 31 December 2030.
Source: S.I. No. 340 of 2026, Class 3A, read 14 October 2026, and the Department's clarification on condition 7.
What is the Class 3A exemption?
Class 3A is an exemption for "the construction, erection or placing of a detached house in the rear garden of a principal house". The Department of Housing calls it a Detached Auxiliary Dwelling. It came into operation on 27 July 2026, and the circular that went to the councils, Circular Letter PLR-02, was published on 17 July 2026.
Citizens Information puts the garden home case plainly: since 27 July 2026 you do not need planning permission to add a small, detached home in your back garden, and to get the exemption the home has to meet the list of conditions.
Getting it wrong is expensive. Doing work that requires planning permission without having it is an offence that can carry very large fines and possible imprisonment. You can apply for permission to retain an unauthorised development, but that can be refused, and then it has to be demolished. So go through the conditions against your own garden before you order anything.
How big can a garden home be?
Between 32 m² and 45 m². Condition 7 sets the floor at "not less than 32 square metres" and then says that taken together with any other such structures previously constructed, erected or placed under Class 3 in the same grounds, the total "shall not exceed 45 square metres".
Class 3 is the exemption the Department's circular describes as a structure in the back garden, such as a shed, store, home office or gym. The circular says that limit will be increased from 25 square metres to 30 square metres. The Department of Housing, Local Government and Heritage issued clarifications on condition 7 of Class 3A on 6 November 2026, and Wicklow County Council publishes them on its website. They say the reference to Class 3 in that condition should be a reference only to Class 3A, and that the new Class 3A should be used only once.
Say you have a semi-d in Swords with a 15 m² timber shed at the bottom of the garden. Under the Department's clarification, the shed does not count towards the 45 m² limit for the garden home; what matters is that at least 25 m² of free garden space is left. So measure the garden you would have left with the shed and the garden home both in place.
How tall can it be?
4 m if it has a tiled or slated pitched roof, and 3 m in any other case. Ask any supplier for the finished height on your own ground, in writing, before you order.
How close to the boundary can it go?
At least 0.6 m from any wall or party boundary, and the regulations add that any windows "should be at least 0.6 metres from the boundary they face". In a narrow terrace garden in Cork, start with the width. Condition 14 takes 0.6 m off each side, so a 6 m wide garden is really 4.8 m of buildable width.
How much garden do you have to keep?
Condition 9 says the structure shall not reduce the total amount of private open space reserved exclusively for the use of the occupants of the house to less than 25 square metres. Pace out what would be left after the garden home, the 0.6 m margins and the path down to its door.
Water, power and wastewater
There is to be "no separate connection to utilities, including water or wastewater utilities". That is what auxiliary means here: gov.ie describes the class as a detached auxiliary dwelling linked to the services of the principal house.
If waste water is treated on the site, with a septic tank or a similar system, condition 13 adds three things. The structure must not encroach on any approved percolation area, the network of shallow underground pipes that carries the liquid out of a septic tank into the soil. The treatment system has to have enough capacity for the extra load and comply with the EPA Code of Practice for Domestic Waste Water Treatment Systems. And no additional waste water treatment units may be installed under this class.
For a bungalow in Mayo on its own tank, that is a question for whoever certifies the system rather than for whoever sells you the unit. And if the percolation area is already at capacity for the house, a second tank is not the way out, because the class does not allow one.
Who can live in it, and can you rent it out?
The garden home can only be occupied in conjunction with the main dwelling house, and it cannot be sold or subdivided separately from it. Two more conditions go with that:
- The exemption applies only where the principal house is the sole or main residence of the property owner at the time the development is commenced.
- The detached dwelling may not be used for the purposes of short-term letting.
Condition 19 rules out short-term letting. If a long-term tenancy is what you have in mind, put that question to your council in writing before you commit to anything, and take tax advice separately.
Access, and the house itself
Three conditions get missed because they are about the rest of the property rather than the new building:
- No new vehicular or pedestrian access onto a road may be constructed under this class.
- Independent pedestrian and wheelchair access to the detached house has to be provided within the grounds of your house. Walk the route a wheelchair would take from the road to the new front door, staying inside your own boundary, before you count on this one. In a mid-terrace it is the condition to check first.
- The exemption cannot be used where the principal house has been subdivided.
Building regulations still apply
Condition 4 says it plainly: "the relevant building control legislation shall apply (such as Building Regulations (including Fire Safety) and Building Control Regulations)". The circular says the same thing: in all cases, any relevant Building and Fire Regulations, including those for habitable dwellings where applicable, will continue to apply.
Read condition 5 twice if you are looking at a unit that arrives complete on a lorry: the construction "shall not be temporary in nature, such as a caravan or mobile home". Whether a particular factory-built unit clears that condition is a question for your council or a planning consultant on your own site, not something to take on anybody's word, including ours.
The 14-day notice to your council
At least 14 days before work starts you have to send the planning authority a notification telling them you intend to use this class of exemption, confirming that the site meets the requirements of the regulations and stating your reason for using it. The notification has to include the location and the Eircode of the property.
The council keeps a record of every notification under the class and reports the numbers to the Minister each year, so uptake is being counted. The circular also gives councils a suggested template, which is worth knowing: ask your planning department which form they want before you write your own letter.
When you still need planning permission
Anything outside the conditions needs permission in the normal way. The usual ones:
- A unit under 32 m² or over 45 m².
- A site that is not the rear garden of a principal house.
- A house that has already been subdivided.
- A build that will not be finished by 31 December 2030.
- Anything you want to sell, subdivide or let short-term.
Dublin City Council also points out that exemptions do not apply if the property is a protected structure, or sits in an Architectural Conservation Area or a Special Amenity Area Order.
If you are not sure which side of the line your garden falls on, section 5 of the Planning and Development Act 2000 lets any person ask the planning authority for a declaration on whether a development is exempt. In Dublin City the application goes in writing with site maps and a fee of €80, and the planner decides within four weeks. On a build this size, that is worth doing before you order anything.
The 2030 deadline
The relevant period for Class 3A began on the day the regulations were signed, 16 July 2026, and ends on 31 December 2030. The exemption applies only to development that is both commenced and completed inside that period, so finishing matters as much as starting: a garden home begun in 2030 and finished in 2031 is not covered.
What to do next
Measure three things before you talk to anyone: the floor area of the home you want, the open space you would have left, and the clear width between your boundaries. After that, ring your planning department and ask what they want in the notification.
Questions people ask
Not if the project meets every condition of the Class 3A exemption, which has applied since 27 July 2026 to a detached house of 32 to 45 m² in the rear garden of a principal house. If any condition is not met, permission is needed in the normal way. A section 5 declaration from your council settles it for your own site.
Not less than 32 m² and not more than 45 m². Under the Department's clarification, a shed already in the garden does not count towards the 45 m²; what matters is that at least 25 m² of free garden space is left.
Up to 4 metres in height if you have a tiled or slated pitched roof, or up to 3 metres if you have a different roof.
Yes. A notification goes to the planning authority at least 14 days before work starts, confirming that the site meets the requirements and stating the reason for using the class, and it must include the location and the Eircode.
Short-term letting is ruled out by condition 19. For a long-term tenancy, ask your council in writing and take tax advice before you let anyone move in.
No. It may only be occupied in conjunction with the main dwelling house and cannot be sold or subdivided separately from it.
31 December 2030. The work has to be both commenced and completed inside the relevant period, which began when the regulations were signed on 16 July 2026.
Sources: S.I. No. 340 of 2026 (Class 3A); Circular Letter PLR-02, Department of Housing, Local Government and Heritage; Citizens Information on planning permission; Dublin City Council on section 5 declarations. All read 14 October 2026. General information, not planning or legal advice: check your own site with your planning authority. How we check these guides.
Thinking about a garden home?
Get a free, no-obligation quote for a garden home in your back garden. Whether a garden home suits your site depends on the Class 3A conditions, so check them for your own property.
More on planning rules and the exemption
What the Class 3A exemption for detached garden homes allows, the conditions you must meet, and when you still need planning permission.
- 45 m² garden home
- Sheds and the 45 m² limit
- Garden room vs garden home
- Boundary distances
- Council notice
- Mobile home in the garden
- Garage to granny flat