Sligo

Modular homes in Sligo

The Sligo County Council template for a garden home notice, the maps a section 5 needs, the timing of the commencement notice, and why radon deserves a close look in this county.

Modular Garden Home supplies and installs modular garden homes behind existing houses in every county, Sligo included. Our 36 m² home is fully installed from €85,000 including VAT. We check every condition at a free site visit, and we send the council's 14-day notice for you.

From€85,000
IncludesVAT & install
Get a FREE Quote No obligation.

Free, no deposit, no obligation. We never share your details. Privacy notice

To put a garden home behind your house in Sligo, you email a completed notice to the council's planning section at least 14 days before work starts. According to Citizens Information, since 27 July 2026 you do not need planning permission to add a small, detached home in your back garden. That exemption has conditions, and the notice is where you confirm you meet them.

The rule behind it

This exemption is called Class 3A. Statutory Instrument 340 of 2026 added it to the planning regulations, and it came into operation on 27 July 2026. The window closes on 31 December 2030: the work has to start and finish by then.

Check two things on your own site first. The garden home must be at least 0.6 metres from any wall or boundary. And building it must not leave your household with less than 25 square metres of private open space. Read the planning rules guide for every condition.

Emailing your notice to Sligo County Council

Sligo has a ready-made Class 3A Detached Auxiliary Dwelling Notification Template on its Submit a Notification page. Fill it in and send it to planning@sligococo.ie. The template itself says a minimum of 14 days' notice is required before the works start.

The template asks for:

  • your name, address with Eircode, phone number and email;
  • where the garden home will go, with its Eircode;
  • the date you plan to start;
  • a yes or no on whether your site meets all the requirements;
  • your reason for the garden home.

A checklist follows. Some lines are worth reading twice before you tick them: the build will be finished before 31 December 2030, any windows will be at least 0.6 metres from the boundary they face, the home will not be used for short-term letting, and the main house is the owner's sole or main residence when the work starts. For more on timing, read the council notice guide.

What the Sligo template says about sheds

One checklist line on Sligo's template counts anything already built under Class 3, such as a shed or garage, toward the 45 square metres.

The Department of Housing has since clarified it. In a note published by Wicklow County Council on 6 November 2026, the Department says the reference to Class 3 in that condition should be a reference only to Class 3A, so the exemption is used once. In practice, it says, the key requirement is that free garden space is no less than 25 square metres, regardless of other structures in the garden. Read the shed guide for worked examples.

A section 5 in Sligo: the maps to draw

If you want the council's formal view on your plan, you apply for a section 5 declaration. Sligo's form goes to the Planning Section, City Hall, Quay Street, Sligo, or by email to planning@sligococo.ie. It asks you to say why you think the work is exempt or not.

Sligo is precise about scales. Send a site location map at 1:2500 and a site layout map at 1:500, along with floor plans, elevations and the €80 fee. The Planning and Development Act 2000 gives the council 4 weeks from receiving the request to issue its declaration.

The commencement notice window

Building control is a separate notice, with its own timing. The Department of Housing's note says a garden home like this needs a commencement notice with additional documentation sent to the building control authority before the work begins.

Sligo's building control page sets the window tightly. Your commencement notice must reach it not less than 14 days and not more than 28 days before you start. The notice and any extra documents are completed online, on the National BCMS (Building Control Management System).

Radon in Sligo

Radon is the local check to take seriously here. In the EPA's county results, to 31 December 2019, 2,698 Sligo houses were measured. Radon is measured in becquerels per cubic metre (Bq/m3). In Sligo, 560 of those houses fell between 200 and 799 Bq/m3, and 111 went over 800. The highest Sligo result was 5,600 Bq/m3. The national reference level for a home is 200, and above that the EPA recommends acting to bring it down.

Sligo County Council's own radon page explains why it matters. Radon has no colour, taste or smell, so only special detectors find it. About 350 cases of lung cancer in Ireland each year are linked to it. Some parts of the country, called high radon areas, are more likely to have a problem. The council also says radon is easy to test for and easy to reduce.

The EPA's radon map lets you search by Eircode. Any new home built in a High Radon Area must have a radon membrane to meet Building Regulations. A home test for the house you have now is done by post over three months, for about €50. The free radon phone line, listed on Sligo's page, is 1800 300 600.

Septic tanks in Sligo

The CSO counted 12,234 registered domestic waste water treatment systems in Sligo in 2024, with 169 new ones registered that year. These are septic tanks and similar systems for homes not connected to a public sewer.

The EPA's account of a septic tank: the liquid that leaves it travels into shallow buried pipes, a network called a percolation area. Building the garden home on top of an approved percolation area is ruled out. Your present treatment system needs enough capacity for the added load, it must follow the EPA Code of Practice, and no additional unit may go in for the garden home. Ahead of any building, the Department of Housing's note says your drainage capacity should be considered.

What a Sligo garden home costs

Our 36 m² garden home is fully installed from €85,000, including VAT. That covers delivery and foundations, connection to your home's water, electricity and drainage, the council's 14-day notice and the Building Regulations paperwork. Your exact price is fixed in writing after a free site check. Get a free quote.

Set aside about €50 for the radon test. A section 5, if you decide you want one, is €80. Everything else is in the garden home cost guide. Close by, there are pages for Mayo and Donegal, and an overview at modular homes in Ireland.

Sligo questions

Email the completed Class 3A template to planning@sligococo.ie, at least 14 days before the works start.

A site location map at 1:2500 and a site layout map at 1:500, plus floor plans, elevations and the €80 fee.

Not less than 14 days and not more than 28 days before you start, completed online on the BCMS.

Of 2,698 Sligo houses in the EPA's results, 111 read above 800 Bq/m3. Check your Eircode on the EPA radon map.

The Department's 6 November 2026 clarification says the reference is to Class 3A only. The test that matters is keeping at least 25 square metres of garden free.

Every source was read on 17 November 2026. They are Sligo County Council, Citizens Information, the EPA, the CSO, and the Department of Housing's 6 November clarification as published by Wicklow County Council.

Treat this page as general guidance rather than planning or legal advice, and confirm your own site with Sligo County Council. How we work.

Thinking about a garden home?

Get a free, no-obligation quote for a garden home in your back garden. Whether a garden home suits your site depends on the Class 3A conditions, so check them for your own property.